Overstrand, Norfolk Coastal Defence
Sector: Costal Defence
Scope: 493 No. GU32N sheet piles
Duration: 5 weeks
Plant: 35T Excavator & Movax Side Grip Pile Driver
Strata: Sand over Clay
GMP were engaged to install approximately 300 linear metres of sheet piling, to replace the the existing sea defences on the beach at Overstrand. The project came with the challenge of working along a public promenade and around the the tide times. Despite the varying tides GMP achieved the client’s expected programme and are looking forward to the next sheet piling scheme.