Gallions View, Woolwich

Sector: Residential
Scope: 1067 No. 350mm, 355 No. 400mm, 25 No. 500mm diameter CFA piles and 9 No. 500mm diameter CFA crane base piles. The design required both working and non working test piles
Duration: 21 weeks  Plant: Llamada P105
Strata: Made Ground and organic material over Kempton Park Gravel over Thanet Sand

This large-scale project was originally programmed for 2 No. rigs due to the pile numbers involved, however, the requirement for the second rig was omitted due to GMP exceeding anticipated productions.